Brisbane to Roma Looping 5 Gas Pipeline

Enewsletter

Sign-up today to receive information on the latest news and projects from HVAC

Latest Project

Legacy Way - TBM Ducting

Client: Transcity is an integrated team comprising BMD Constructions, Italian company Ghella and Spanish company Acciona. T...

Latest News

Strength through diversity

Andrew Clarke and Gordon Waddell talked to the Australian Resource Focus publication about HVAC and how the companies diversity...

Brisbane to Roma Looping 5 Gas Pipeline

oil3

Project: Brisbane to Roma Looping 5 Gas Pipeline

Location: Dalby, Queensland

Client: Agility/ Clough Lucas Joint Venture

Scope of work: Receipt of free issued materials, provision of miscellaneous materials, fabrication, testing, assembly, painting, documentation, disassembly, packaging, storage, quality control and loading of pre-fabricated assemblies to be used to the CS Energy Expansion – RBP Stage 5, Natural Gas Pipeline

Value: $400,000

Challenge: Find a fabrication company who can prefabricate, test, and delivery specific items for a major pipeline project

Engineering solutions: HVAC was able to complete all mechanical materials and components and then subject them to internal pressure tests as per Section 3 of AS2885.1. All welding and welded joints complied with AS2885.2